Systems
Plant Yates — JAC GT-proper IC&E · readiness to first fire, by systemUnit 3
3 systems10%GT enclosureGTENCfirst-fire12%
Construction
Mechanical complete
Pre-commissioning
Ready for commissioning
Commissioned
Conduit1,800 ft
20%
Cable5,200 ft
10%
Device/instrument42 ea
12%
Termination312 ea
11%
Loop20 ea
0%
Fuel gasFGfirst-fire8%
Construction
Mechanical complete
Pre-commissioning
Ready for commissioning
Commissioned
Conduit1,440 ft
14%
Cable4,160 ft
6%
Device/instrument34 ea
8%
Termination250 ea
6%
Loop16 ea
0%
Lube oilLOfirst-fire8%
Construction
Mechanical complete
Pre-commissioning
Ready for commissioning
Commissioned
Conduit1,260 ft
15%
Cable3,640 ft
7%
Device/instrument29 ea
8%
Termination218 ea
7%
Loop14 ea
0%