Plant Yates — JAC GT-proper IC&E · open items carry over automatically+ New entry

Open constraints (4)

first-fireTCC · owner Vendor10d open
Control cabinet internal terminations pending vendor cabinet rev
needs: Vendor to confirm cabinet revision
first-fireFG · owner B&V7d open
Missing revised cable schedule blocks fuel-gas terminations
needs: Issue revised drawing
HYD · owner Beltline5d open
Hydraulic skid access blocked by scaffold not yet removed
needs: Remove scaffold / resequence
FANDG · owner GP4d open
Detector calibration gas not on site
needs: Procure cal gas

Open quality / rework (3)

reworkfirst-fireU1 · LO · segregation · BeltlineJun 25
Analog/digital signal segregation not maintained in tray run
reworkU1 · GTENC · support · BeltlineJun 24
Cable support spacing exceeds spec in two runs
reworkU2 · FG · termination · BeltlineJun 23
Terminations landed without ferrules per spec

Recent field observations

U1 · FGTeam A · Beltline ×607:1015:30Jun 26
Conduit routing + cable pull, fuel-gas skid · Pulled ~180 ft; held on tray segregation · 180 ft conduit · 1-FG-ISO-002
U1 · GTENCTeam B · Beltline ×407:0015:00Jun 25
Device mounting, enclosure instruments · Mounted 5, wired 3 · 5 devices · 1-GTENC-LP-014
U2 · GTENCTeam C · Beltline ×507:1514:40Jun 24
Conduit install, GT enclosure · ~150 ft installed · 150 ft conduit · 2-GTENC-CD-006