Plant Yates — JAC GT-proper IC&E
Georgia Power · sponsor Mitsubishi Power · EPC Black & Veatch
Friday, June 26, 2026
8%
First-fire readiness
1/13 critical turned over
Jan 4, 29
First-fire forecast
data-driven
3
Open first-fire risks
blockers + quality
37%
Overall GT IC&E
MH-weighted earned
1
Rework prevented
to date · issues caught early
$56k
Cost avoided
to date · GTS-protected $
Path to first fire
Unit 156% earned
Mobilized
Construction
Mechanical Complete
Pre-Comm
RFC / Turnover
First Fire
Unit 231% earned
Mobilized
Construction
Mechanical Complete
Pre-Comm
RFC / Turnover
First Fire
Unit 310% earned
Mobilized
Construction
Mechanical Complete
Pre-Comm
RFC / Turnover
First Fire
Work observed
| Unit | System | Contractor | MP | Hours | Work / quantity |
|---|---|---|---|---|---|
| U1 | FG | Beltline | 6 | 07:10–15:30 | Pulled ~180 ft; held on tray segregation · 180 ft conduit · 1-FG-ISO-002 |
Progress logged
No progress quantities logged on this day.
GTS advisement & intervention
No advisement events logged on this day.
Quality & rework
No deficiencies logged on this day.
Open constraints — carryover register (4)
| Unit | System | Constraint | Owner | Needed action | Age | FF |
|---|---|---|---|---|---|---|
| U1 | TCC | Control cabinet internal terminations pending vendor cabinet rev | Vendor | Vendor to confirm cabinet revision | 10d | Yes |
| U2 | FG | Missing revised cable schedule blocks fuel-gas terminations | B&V | Issue revised drawing | 7d | Yes |
| U1 | HYD | Hydraulic skid access blocked by scaffold not yet removed | Beltline | Remove scaffold / resequence | 5d | — |
| U1 | FANDG | Detector calibration gas not on site | GP | Procure cal gas | 4d | — |
Open quality items — carryover (3)
| Unit | System | Deficiency | Category | Party | Rework |
|---|---|---|---|---|---|
| U1 | LO | Analog/digital signal segregation not maintained in tray run | segregation | Beltline | Yes |
| U1 | GTENC | Cable support spacing exceeds spec in two runs | support | Beltline | Yes |
| U2 | FG | Terminations landed without ferrules per spec | termination | Beltline | Yes |