Gulf Turbine ServicesDaily Field Report

Plant Yates — JAC GT-proper IC&E

Georgia Power · sponsor Mitsubishi Power · EPC Black & Veatch
Friday, June 26, 2026
8%
First-fire readiness
1/13 critical turned over
Jan 4, 29
First-fire forecast
data-driven
3
Open first-fire risks
blockers + quality
37%
Overall GT IC&E
MH-weighted earned
1
Rework prevented
to date · issues caught early
$56k
Cost avoided
to date · GTS-protected $

Path to first fire

Unit 156% earned
Mobilized
Construction
Mechanical Complete
Pre-Comm
RFC / Turnover
First Fire
Unit 231% earned
Mobilized
Construction
Mechanical Complete
Pre-Comm
RFC / Turnover
First Fire
Unit 310% earned
Mobilized
Construction
Mechanical Complete
Pre-Comm
RFC / Turnover
First Fire

Work observed

UnitSystemContractorMPHoursWork / quantity
U1FGBeltline607:1015:30Pulled ~180 ft; held on tray segregation · 180 ft conduit · 1-FG-ISO-002

Progress logged

No progress quantities logged on this day.

GTS advisement & intervention

No advisement events logged on this day.

Quality & rework

No deficiencies logged on this day.

Open constraints — carryover register (4)

UnitSystemConstraintOwnerNeeded actionAgeFF
U1TCCControl cabinet internal terminations pending vendor cabinet revVendorVendor to confirm cabinet revision10dYes
U2FGMissing revised cable schedule blocks fuel-gas terminationsB&VIssue revised drawing7dYes
U1HYDHydraulic skid access blocked by scaffold not yet removedBeltlineRemove scaffold / resequence5d
U1FANDGDetector calibration gas not on siteGPProcure cal gas4d

Open quality items — carryover (3)

UnitSystemDeficiencyCategoryPartyRework
U1LOAnalog/digital signal segregation not maintained in tray runsegregationBeltlineYes
U1GTENCCable support spacing exceeds spec in two runssupportBeltlineYes
U2FGTerminations landed without ferrules per specterminationBeltlineYes
Prepared by Gulf Turbine Services — IC&E TFA field team. GTS provides field execution intelligence on GT-proper; value is measured as issues caught early, rework prevented, and first-fire schedule protected — not craft production rate. Confidential — for Georgia Power / Mitsubishi Power use.