GTS Value Ledger
Plant Yates — JAC GT-proper IC&E · the case to keep the crew7
Value events
1
Rework prevented
$56k
Cost avoided
3d
Schedule protected
1 advisements ignored
Rework preventedJun 24 · U1 · GTENC· Beltline2d$18k
Conduit route conflicted with enclosure access panel; advised reroute above tray before cable pull.
Advisement ignored → reworkJun 23 · U1 · LO· Beltline$9k
Advised label scheme per spec; crew used field labels; now re-labeling 40+ terminations.
advisement not followed — rework resulted
Cost avoidanceJun 22 · U2 · GTENC· GTS$26k
Shorter raceway route identified — ~220 ft conduit + cable avoided.
ConstructabilityJun 21 · U1 · FANDG· GTS
Recommended detector mounting sequence to keep maintenance access clear post-startup.
Bad decision stoppedJun 20 · U1 · TCC· Beltline1d$12k
Crew about to land control wiring to wrong cabinet section; stopped before termination.
Issue foundJun 19 · U2 · FG· B&Vclosed5d
Missing cable schedule revision — terminations blocked; escalated to B&V for revised drawing.
advisement not followed — rework resulted
AccountabilityJun 18 · U1 · HYD· Beltlineclosed
Pressed daily on open punch closure; 11 of 17 items closed this week.