First-Fire Readiness
Plant Yates — JAC GT-proper IC&E · Georgia PowerGTS field execution intelligence on GT-proper. Value = issues caught early, rework prevented, first-fire schedule protected — not craft production rate (GTS advises union craft, does not control pace).
8%
First-fire readiness
1/13 critical systems turned over
Critical
First-fire status
Jan 4, 29
First-fire forecast
1d pulled in
37%
Overall GT IC&E
MH-weighted earned
3
First-fire risks
open blockers
1
Rework prevented
1 issues found
$56k
Cost avoided
5 open value items
Path to first fire
by unit · weakest critical systemUnit 156% earned
Mobilized
Construction
Mechanical Complete
Pre-Comm
RFC / Turnover
First Fire
Unit 231% earned
Mobilized
Construction
Mechanical Complete
Pre-Comm
RFC / Turnover
First Fire
Unit 310% earned
Mobilized
Construction
Mechanical Complete
Pre-Comm
RFC / Turnover
First Fire
Unit readiness
ScheduleAll systemsUnit 156%
6 systems · 6 first-fire-critical · 4 red
Unit 231%
4 systems · 4 first-fire-critical · 2 red
Unit 310%
3 systems · 3 first-fire-critical
Needs attention
top critical / behindU2 · Fire & gasConstruction15%
U1 · Turbine control cabinetfirst-fire blockerConstruction22%
U2 · Fuel gasfirst-fire blockerConstruction29%
U1 · Hydraulic oilConstruction35%
U1 · Fire & gasMechanical complete51%
U1 · Fuel gasMechanical complete65%
GTS value — recent
Value ledgerRework preventedU1 · GTENC$18k
Conduit route conflicted with enclosure access panel; advised reroute above tray before cable pull.
Advisement ignored → reworkU1 · LO$9k
Advised label scheme per spec; crew used field labels; now re-labeling 40+ terminations.
Cost avoidanceU2 · GTENC$26k
Shorter raceway route identified — ~220 ft conduit + cable avoided.
ConstructabilityU1 · FANDG
Recommended detector mounting sequence to keep maintenance access clear post-startup.
Bad decision stoppedU1 · TCC$12k
Crew about to land control wiring to wrong cabinet section; stopped before termination.
Issue foundU2 · FG
Missing cable schedule revision — terminations blocked; escalated to B&V for revised drawing.
Open constraints
Field logfirst-fireTCC · Vendor10d open
Control cabinet internal terminations pending vendor cabinet rev
first-fireFG · B&V7d open
Missing revised cable schedule blocks fuel-gas terminations
HYD · Beltline5d open
Hydraulic skid access blocked by scaffold not yet removed
FANDG · GP4d open
Detector calibration gas not on site