Systems

Plant Yates — JAC GT-proper IC&E · readiness to first fire, by system

Unit 1

6 systems56%
GT enclosureGTENCfirst-fire85%
Construction
Mechanical complete
Pre-commissioning
Ready for commissioning
Commissioned
Conduit1,800 ft
93%
Cable5,200 ft
85%
Device/instrument42 ea
83%
Termination312 ea
88%
Loop20 ea
63%
Fuel gasFGfirst-fire65%
Construction
Mechanical complete
Pre-commissioning
Ready for commissioning
Commissioned
Conduit1,440 ft
75%
Cable4,160 ft
63%
Device/instrument34 ea
63%
Termination250 ea
66%
Loop16 ea
44%
Lube oilLOfirst-fireblocker73%
Construction
Mechanical complete
Pre-commissioning
Ready for commissioning
Commissioned
Conduit1,260 ft
83%
Cable3,640 ft
71%
Device/instrument29 ea
71%
Termination218 ea
74%
Loop14 ea
50%
Fire & gasFANDGfirst-fire51%
Construction
Mechanical complete
Pre-commissioning
Ready for commissioning
Commissioned
Conduit900 ft
61%
Cable2,600 ft
49%
Device/instrument21 ea
49%
Termination156 ea
52%
Loop10 ea
25%
Hydraulic oilHYDfirst-fire35%
Construction
Mechanical complete
Pre-commissioning
Ready for commissioning
Commissioned
Conduit1,080 ft
45%
Cable3,120 ft
33%
Device/instrument25 ea
34%
Termination187 ea
36%
Loop12 ea
13%
Turbine control cabinetTCCfirst-fireblocker22%
Construction
Mechanical complete
Pre-commissioning
Ready for commissioning
Commissioned
Conduit1,620 ft
31%
Cable4,680 ft
20%
Device/instrument38 ea
21%
Termination281 ea
22%
Loop18 ea
6%