Systems

Plant Yates — JAC GT-proper IC&E · readiness to first fire, by system

Unit 2

4 systems31%
GT enclosureGTENCfirst-fire41%
Construction
Mechanical complete
Pre-commissioning
Ready for commissioning
Commissioned
Conduit1,800 ft
51%
Cable5,200 ft
39%
Device/instrument42 ea
39%
Termination312 ea
42%
Loop20 ea
18%
Fuel gasFGfirst-fireblocker29%
Construction
Mechanical complete
Pre-commissioning
Ready for commissioning
Commissioned
Conduit1,440 ft
39%
Cable4,160 ft
27%
Device/instrument34 ea
26%
Termination250 ea
30%
Loop16 ea
9%
Lube oilLOfirst-fire33%
Construction
Mechanical complete
Pre-commissioning
Ready for commissioning
Commissioned
Conduit1,260 ft
43%
Cable3,640 ft
31%
Device/instrument29 ea
31%
Termination218 ea
34%
Loop14 ea
11%
Fire & gasFANDGfirst-fire15%
Construction
Mechanical complete
Pre-commissioning
Ready for commissioning
Commissioned
Conduit900 ft
23%
Cable2,600 ft
14%
Device/instrument21 ea
16%
Termination156 ea
14%
Loop10 ea
0%