Systems

Plant Wansley — 2×1 CC IC&E · readiness to first fire, by system

Unit 2

2 systems8%
GT enclosureGTENCfirst-fire9%
Construction
Mechanical complete
Pre-commissioning
Ready for commissioning
Commissioned
Conduit1,800 ft
15%
Cable5,200 ft
7%
Device/instrument42 ea
9%
Termination312 ea
7%
Loop20 ea
0%
Fuel gasFGfirst-fire6%
Construction
Mechanical complete
Pre-commissioning
Ready for commissioning
Commissioned
Conduit1,440 ft
13%
Cable4,160 ft
5%
Device/instrument34 ea
6%
Termination250 ea
5%
Loop16 ea
0%