Plant Wansley — 2×1 CC IC&E
Georgia Power · sponsor Mitsubishi Power · EPC Kiewit
Friday, June 26, 2026
0%
First-fire readiness
0/5 critical turned over
Jun 21, 29
First-fire forecast
data-driven
1
Open first-fire risks
blockers + quality
16%
Overall GT IC&E
MH-weighted earned
1
Rework prevented
to date · issues caught early
$14k
Cost avoided
to date · GTS-protected $
Path to first fire
Unit 122% earned
Mobilized
Construction
Mechanical Complete
Pre-Comm
RFC / Turnover
First Fire
Unit 28% earned
Mobilized
Construction
Mechanical Complete
Pre-Comm
RFC / Turnover
First Fire
Work observed
| Unit | System | Contractor | MP | Hours | Work / quantity |
|---|---|---|---|---|---|
| U1 | GTENC | Kiewit | 4 | 07:00–15:30 | ~110 ft installed · 110 ft conduit · 1-GTENC-CD-003 |
Progress logged
No progress quantities logged on this day.
GTS advisement & intervention
No advisement events logged on this day.
Quality & rework
No deficiencies logged on this day.
Open constraints — carryover register (2)
| Unit | System | Constraint | Owner | Needed action | Age | FF |
|---|---|---|---|---|---|---|
| U1 | FG | Fuel-gas P&ID rev pending — instrument index not final | Kiewit | Release P&ID rev C | 6d | Yes |
| U2 | GTENC | Enclosure not weather-tight; conduit install paused | Kiewit | Complete enclosure roof panels | 4d | — |