Gulf Turbine ServicesDaily Field Report

Plant Wansley — 2×1 CC IC&E

Georgia Power · sponsor Mitsubishi Power · EPC Kiewit
Friday, June 26, 2026
0%
First-fire readiness
0/5 critical turned over
Jun 21, 29
First-fire forecast
data-driven
1
Open first-fire risks
blockers + quality
16%
Overall GT IC&E
MH-weighted earned
1
Rework prevented
to date · issues caught early
$14k
Cost avoided
to date · GTS-protected $

Path to first fire

Unit 122% earned
Mobilized
Construction
Mechanical Complete
Pre-Comm
RFC / Turnover
First Fire
Unit 28% earned
Mobilized
Construction
Mechanical Complete
Pre-Comm
RFC / Turnover
First Fire

Work observed

UnitSystemContractorMPHoursWork / quantity
U1GTENCKiewit407:0015:30~110 ft installed · 110 ft conduit · 1-GTENC-CD-003

Progress logged

No progress quantities logged on this day.

GTS advisement & intervention

No advisement events logged on this day.

Quality & rework

No deficiencies logged on this day.

Open constraints — carryover register (2)

UnitSystemConstraintOwnerNeeded actionAgeFF
U1FGFuel-gas P&ID rev pending — instrument index not finalKiewitRelease P&ID rev C6dYes
U2GTENCEnclosure not weather-tight; conduit install pausedKiewitComplete enclosure roof panels4d
Prepared by Gulf Turbine Services — IC&E TFA field team. GTS provides field execution intelligence on GT-proper; value is measured as issues caught early, rework prevented, and first-fire schedule protected — not craft production rate. Confidential — for Georgia Power / Mitsubishi Power use.