Schedule & First-Fire Forecast
Plant Wansley — 2×1 CC IC&E · as of Jun 26, 26GTS-recommended baseline vs actual earned progress. The first-fire date is driven by the data — the latest-finishing first-fire-critical system, projected from its demonstrated install rate. B&V never sequenced GT-proper; this curve is GTS's.
Jun 21, 29
First-fire forecast
set by U2 · Fuel gas
66d pulled in
Forecast trend
vs last week
high
Forecast confidence
all critical forecastable
16% / 5%
Earned vs planned
actual / baseline
3.47
Schedule index (SPI)
earned ÷ planned
16%
Overall earned
MH-weighted
Planned vs actual (job S-curve)
MH-weighted earned %System schedule performance
behind firstU2 · Fuel gasfirst-fireOn track
actual 6%planned 0%SPI 26.50forecast Jun 21, 29plan Jan 15, 27888d late
U2 · GT enclosurefirst-fireOn track
actual 9%planned 0%SPI 31.82forecast Sep 3, 28plan Jan 8, 27605d late
U1 · Fuel gasfirst-fireblockerOn track
actual 18%planned 8%SPI 2.39forecast May 28, 27plan Nov 20, 26190d late
U1 · Lube oilfirst-fireOn track
actual 22%planned 7%SPI 3.12forecast Mar 22, 27plan Nov 27, 26116d late
U1 · GT enclosurefirst-fireOn track
actual 25%planned 8%SPI 2.99forecast Feb 5, 27plan Nov 13, 2684d late