First-Fire Readiness

Plant Wansley — 2×1 CC IC&E · Georgia Power

GTS field execution intelligence on GT-proper. Value = issues caught early, rework prevented, first-fire schedule protected — not craft production rate (GTS advises union craft, does not control pace).

0%
First-fire readiness
0/5 critical systems turned over
Critical
First-fire status
Jun 21, 29
First-fire forecast
66d pulled in
16%
Overall GT IC&E
MH-weighted earned
1
First-fire risks
open blockers
1
Rework prevented
1 issues found
$14k
Cost avoided
1 open value items

Path to first fire

by unit · weakest critical system
Unit 122% earned
Mobilized
Construction
Mechanical Complete
Pre-Comm
RFC / Turnover
First Fire
Unit 28% earned
Mobilized
Construction
Mechanical Complete
Pre-Comm
RFC / Turnover
First Fire

Unit readiness

ScheduleAll systems

Needs attention

top critical / behind
U1 · Fuel gasfirst-fire blockerConstruction18%

GTS value — recent

Value ledger
Issue foundU1 · FG
Cable tray fill exceeds NEC at fuel-gas riser — flagged before pull.
Rework preventedU1 · GTENC$8k
Advised conduit support relocation clear of access panel before concrete.
Cost avoidanceU1 · LO$6k
Combined two lube-oil instrument home-runs — ~120 ft saved.

Open constraints

Field log
first-fireFG · Kiewit6d open
Fuel-gas P&ID rev pending — instrument index not final
GTENC · Kiewit4d open
Enclosure not weather-tight; conduit install paused