Systems

Plant Wansley — 2×1 CC IC&E · readiness to first fire, by system

Unit 1

3 systems22%
GT enclosureGTENCfirst-fire25%
Construction
Mechanical complete
Pre-commissioning
Ready for commissioning
Commissioned
Conduit1,800 ft
35%
Cable5,200 ft
23%
Device/instrument42 ea
23%
Termination312 ea
26%
Loop20 ea
8%
Fuel gasFGfirst-fireblocker18%
Construction
Mechanical complete
Pre-commissioning
Ready for commissioning
Commissioned
Conduit1,440 ft
27%
Cable4,160 ft
17%
Device/instrument34 ea
17%
Termination250 ea
18%
Loop16 ea
3%
Lube oilLOfirst-fire22%
Construction
Mechanical complete
Pre-commissioning
Ready for commissioning
Commissioned
Conduit1,260 ft
31%
Cable3,640 ft
20%
Device/instrument29 ea
20%
Termination218 ea
22%
Loop14 ea
4%